The short version
- The New Pantai Expressway (NPE) is getting a 15 km, fully elevated extension from the Pantai Dalam toll plaza to the Jalan Istana interchange, via Jalan Syed Putra.
- The government approved it in May 2025. IJM signed the supplemental concession agreement on 27 August 2025.
- Construction cost is about RM1.4 billion, funded by the concessionaire, with completion targeted for 2029.
What was approved
The Ministry of Works approved the NPE extension in May 2025. The new stretch adds 15 km to the existing 19.6 km expressway, with a new toll plaza at Syed Putra. IJM has said the project is fully funded by the concessionaire, with no government funding, and that financing of up to RM1.4 billion has been lined up with two financial institutions.
Under the August 2025 agreement, the concession period is extended to cover the new section, and existing NPE toll rates are maintained until the original concession expiry.
Timeline
Work was scheduled to start in the second half of 2025, with completion targeted within about 48 months, which points to 2029. We haven't seen a public progress update since, so check IJM's announcements for the latest status.
What it means for Pantai Sentral Park
The extension starts right at Pantai Dalam, beside Pantai Sentral Park. IJM projects about RM5.6 billion in economic spillover from the project, mainly around Bangsar South and Pantai Sentral Park. For Enlace Suites 2 residents, it means a more direct elevated route towards Jalan Syed Putra and the city centre, on top of the existing links to the Federal Highway, Sprint and the KL–Putrajaya Expressway.
Enlace Suites 2 is expected to complete in March 2030, after the extension's target date. See the location page for the full picture, or the latest prices.
Sources: IJM press release, May 2025 · IJM press release, August 2025 · Free Malaysia Today, 27 August 2025